CURRENT BUDGET REPORT

81ST Avenue Community Library
FUNDING SOURCES
Proposition 14 State Grant $6,513,345
Coliseum Redevelopment set-aside $4,000,000
Measure Q Bond Measure $30,000
Oakland Unified School District $497,065
Stopwaste.Org $80,000
Grants and Donations $515,700
   
Total Funding $11,636,110
   
BUDGET
Design & Engineering $1,600,000
Project & Construction Management $807,509
Construction $8,887,196
Fixtures, Furnishings & Equipment $1,378,920
Inspections and Permits $203,000
Public Art $115,000
Misc $14,000
   
Total Estimated Project Cost $14,300,000
   


Quick Facts
Special Features
Frequently Asked Questions
Design Plans (Nov 2006)
  Ground Floor
Second Floor
Exterior elevation – West and North
Exterior elevation – East and South
Project Status
Budget
Public Art Information
  Project Rendering
Artist Biography
Bond Administration Office
ACORN Woodland School
Oakland Public Library Master Plan - see page 72
 
 

Website Index | Privacy Policy | Contact Us

Change Text Size

Page Last Edited April 21, 2008